POWER SECTOR CREDENTIALS : GE GRID/ALSTOM
COUNRTY / TOWN
SCOPE OF WORK
- Seafreight, customs clearance, ship off- loading at Djibouti port, placement onto plinth, and final delivery to various sites in southern and western Ethiopia
- Project support: road study carried out in anticipation, deployment of exceptional transport teams, technical assistance and safety
- Operations started in 2013
KEY FIGURES
- 8 exceptional convoys for an average distance covered of 1200 km
- Types of equipment transported from china: 9 transformers, 3 reactors, accessories and substation equipment
- Deliveries at 6 locations in Ethiopia: Gambella,Wolkite,Hosaina,Jima and Metu
- Off-loading operations: ship gears, standard lowed , trailers & modular trailers
- 2,500 tons of accessories, bulk goods and 400 TEUS handled
- 12 trucks for the transport of the reactors and 40 trucks containing bulk goods
- 8 people dedicated to a 18-month project
Client
|
Country
|
Project Name |
Scope of Work |
Year |
ELSEWEDY |
Ethiopia |
EEP Supply Project |
Transport of Transformers, Reactors and Substation materials/ accessories EEPCO substation refurbishment. |
2011 |
Vergnet-Alstom |
Ethiopia |
Ashegoda |
Clearing & delivery of transformers, reactors & accessories from Djibouti to various sites in Southern and Western Ethiopia, including off-loading and placing onto plinth. |
2013 |
Alstom |
Ethiopia |
ETSPII |
Transport of Transformers, Reactors and Substation materials |
2014 |
Apar Industries |
Ethiopia |
EEP Supply Project |
Clearance/Transport and deliveries of cables / transmission materials (Containerized Cargo 250 TEUs) |
2015 |
Henan Kosen |
Ethiopia |
EEP Supply Project |
Clearance/Transport and deliveries of cables / transmission materials (Containerized Cargo 500 TEUS) |
2017 |